CP1273 – Changes to the scope of CoP10 to cover current transformer operated Meters
Formal title: Changes to the scope of CoP10 to cover current transformer operated Meters
Current Status
Summary
E. ON raised CP1273, which proposes widening the scope of CoP10. CoP10 would include CT operated Meters. This would allow Registrants have the choice of installing a less expensive CoP10 Meter where they envisage a site’s demand remaining below the mandatory HH threshold (100kW), despite requiring CT metering. Alternatively, the Registrant could chose to install a more expensive CoP5 Meter (or above), to meet the requirements for mandatory HH metering should the site’s demand exceed the mandatory HH threshold in the future.
Progression
CP1273 was raised on 6 January 2009. CP1273 was issued for Industry Impact Assessment as part of CPC00651. CP1273 presented to the SVG on 3 March 2009 for decision on progression. The SVG approved CP1273 for inclusion in the June 2009 Release. CP1273 was implemented on 25 June 2009 as part of the June 2009 Release.