Change Proposal: CP1301

Registration Requirements for System Connection Points Between Onshore Distribution Systems and Offshore Transmission Systems [Closed]

Proposer Name: ELEXON

Current Phase: Implemented

Category: CVA

Lead Analyst: Stuart Holmes

Responsible Panel Committee: Imbalance Settlement Group (ISG)

Summary

For some time now, BERR and Ofgem have been developing a new regulatory regime for Offshore licensed Transmission Systems. In June 2009 the Secretary of State approved changes to the Balancing and Settlement Code. The approved changes are now in the relevant sections of the BSC. CP1301 recommends that these changes are reflected in the relevant Code Subsidiary Documents.

History

CP1301 was raised on 03 July 2009. CP1301 was issued for Industry Impact Assessment as part of CPC00666. The ISG approved this CP and it was implemented as part of the  February 2010 BSC Systems Release.

Documents

CP1301  [48.2 Kb]
Event: CP1301 raised
Event Date: 3 July 2009

CP1301_Attachment A  [33.8 Kb]
Event: CP1301 raised
Event Date: 3 July 2009

CP1301 Attachment B  [17.6 Kb]
Event: CP1301 raised
Event Date: 3 July 2009

Response     [134.8 Kb]
Event Date: 31 July 2009