CP1354 – Clarifying commissioning requirements of BSCP537 Qualification Appendix 1: Self Assessment Document (SAD)

Formal title: Clarifying commissioning requirements of BSCP537 Qualification Appendix 1: Self Assessment Document (SAD)

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

The proposed change has been raised by Elexon. It is intended to help applicants to be more fully aware of their Qualification requirements and therefore better able to fulfil the requirements for the commissioning process.

Progression

CP1354 was raisedand issued for industry impact assessment via CPC00701 on 2 September 2011, with responses due back on 29 September 2011. CP1354 was approved by the ISG and SVG at their meetings on 25 October and 1 November 2011 respectively.