CP1418 – Validation of D0041 flows

Formal title: Validation of D0041 flows

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

This CP proposes to introduce an additional step to the SVAA validation of the D0041 flow to ensure that there are no duplicate PC/Distributor/LLFC/SSC/TPR rows within a flow.

Progression

CP1418 was raised by Elexon on 1 July 2014 and was issued for CPC Consultation. The SVG approved CP1418 at its meeting on 2 September 2014 for implementation on 26 February 2015 as part of the February 2015 BSC Systems Release.