When do you use the [Bulk Change of Non Half Hourly Agent] process?

The process is mandatory where the number of NHH Metering Systems planned for the change of agent exceeds the threshold. This threshold is approved by the BSC Panel (see BSC Section J 4.2.5) and is currently set at 20,000 per day per SMRA.

The process takes two different paths depending on whether the change is enforced:

  • If a Supplier Agent breaches its contractual obligations, has its Qualified status removed, or goes into liquidation then the change is enforced.
  • If a Supplier wishes to change Supplier Agent the change is not enforced.