Summary

P280 wishes to introduce new Measurement Classes for Half Hourly-settled customers in the Domestic and SME markets, and to require the Supplier Volume Allocation Agent (SVAA) to provide Distributors with aggregated Half Hourly consumption data for Metering Systems registered to those new Measurement Classes.

History

P280 was raised by ENW on 29 November 2012. The Panel agreed to issue it for an Assessment Procedure by a Workgroup, during which P280 underwent two Workgroup Assessment Consultations. The Workgroup recommended that P280 should be approved, and its Assessment Report was presented to the Panel at its meeting on 14 June 2012.

The Panel initially recommended that P280 should be approved, and issued P280 for its Report Phase Consultation. The Panel made its final recommendation that P280 should be approved at its meeting on 9 August 2012. P280 was rejected by Ofgem on 6 November 2012.

Documents

P280 National Grid Direction Letter  [19.7 Kb]
Event: P280 National Grid Direction Letter received
Event Date: 6 November 2012

P280 Authority Decision  [155.5 Kb]
Event: P280 Authority Decision received
Event Date: 6 November 2012

P280 Final Modification Report  [1.3 Mb]
Event: P280 Final Modification Report sent to Authority
Event Date: 10 August 2012

P280 Draft Modification Report (Panel 201/04)  [1.3 Mb]
Event: P280 Draft Modification Report presented to Panel
Event Date: 3 August 2012

P280 Report Phase Consultation Responses  [299.1 Kb]
Event: P280 Report Phase Consultation Responses received
Event Date: 3 August 2012

P280 Report Phase Consultation  [2.5 Mb]
Event: P280 Report Phase Consultation issued
Event Date: 15 June 2012

P280 Assessment Report (Panel 199/05)  [1.3 Mb]
Event: P280 Assessment Report presented to Panel
Event Date: 8 June 2012

P280 Second Assessment Consultation Responses  [627.4 Kb]
Event: P280 Second Assessment Consultation Responses received
Event Date: 21 May 2012

P280 Second Assessment Consultation  [1.0 Mb]
Event: P280 Second Assessment Consultation issued
Event Date: 30 April 2012

P280 Assessment Consultation Responses  [579.3 Kb]
Event: P280 Assessment Consultation Responses received
Event Date: 5 March 2012

P280 Assessment Consultation  [1.4 Mb]
Event: P280 Assessment Consultation issued
Event Date: 13 February 2012

P280 Initial Written Assessment (Panel 190/05)  [270.3 Kb]
Event: P280 IWA presented to Panel
Event Date: 8 December 2011

P280 Proposal Form  [46.0 Kb]
Event: P280 raised
Event Date: 29 November 2011