Error and Failure Resolution

The Error and Failure (E & F) Resolution Process is a key preventative, detective and corrective process within the Performance Assurance Framework (PAF).

The information presented in this section is designed to explain the E & F Resolution Process and also to provide advice and guidance to market participants to help resolve or prevent common problems associated with market operations. ELEXON aims to encourage all participants to rectify errors using an agreed and formalised practice and approach.

Detection

The techniques that make up the PAF, including the Audit, Technical Assurance, and Reporting and Monitoring are used by ELEXON to identify potential or existing operational performance issues with BSC Parties and Party Agents. Issues may also be identified by participants themselves or in contact between participants and their Operational Support Managers (OSMs).

When an issue is identified, ELEXON will contact the relevant participant to obtain more information and the issue is captured with the Performance Issue Management Process to ensure the impact of the issue on Settlement process is fully understood and to ensure that the corrective actions in place are appropriate.

Problem Proforma

The Error and Failure Resolution technique is an internal process which allows ELEXON to monitor the progress of performance problems. When an issue that has been detected is determined to materially affect the accuracy of balancing and settlement, excessively disrupts the operation of balancing and settlement, or causes non compliance with the BSC, for any Settlement date, ELEXON will request the completion of a Problem Proforma.

The objective of the problem proforma is to:

  • Inform ELEXON of the causes of the problem, its impact and the corrective action being taken
  • Assure ELEXON that the problem is fully understood, that corrective action is appropriate and that the problem is under control
  • Enable ELEXON to monitor the resolution

Problem Proformas are reviewed by ELEXON. This process includes ensuring that it adheres to the problem proforma guidelines and that the corrective action is robust. Comments are returned to the participant to incorporate them in the proforma before sending it back to ELEXON. This process is repeated until the proforma is satisfactory, at which point it is baselined (agreed as finalised) by ELEXON.

Resolution Monitoring

Each corrective action on the proforma will require a milestone, set by the participant and agreed with ELEXON, which the participant will be monitored against. When a milestone is reached ELEXON requires confirmation from the participant in addition to corresponding observable effects in settlement, consistent with that milestone being achieved. If target completion dates are not met, revised dates may be submitted with approval from ELEXON and when all milestones have been achieved a problem is deemed ready to be closed.

Closure

Closure of any issue can only be made when both the participant and ELEXON confirm that the problem has been resolved. Issues that have been detected by the BSC Operational Audit may also be deemed closed by ELEXON however Audit Issue Documents can only be closed with agreement from the BSC Auditor following a site visit.

Escalation Procedure:

The escalation procedure will be initiated when:

  • The problems being experienced by a BSC Party or Party Agent are sufficiently serious in their impact on Settlements or their impact on other BSC Parties
  • The overall Performance Issue Management Process breaks down. This may be caused by a Party’s lack of openness, lack of commitment, failure to provide satisfactory problem proformas, lack of understanding of causes of issues, or inappropriate corrective action

If a problem passes through the escalation procedure without resolution, the ELEXON escalation process interfaces with the Performance Assurance Board’s (PAB) Escalation Cycle (refer to BSCP 534 for further information) in order to assist the resolution of the issue.

The diagram below outlines the various levels within the ‘internal’ ELEXON escalation process prior to referring a BSC Party or Party Agent to the PAB’s escalation cycle.

ELEXON Escalation Process

ELEXON Escalation Process

Explanation of ELEXON Escalation Process diagram

The ELEXON Escalation Process starts with the detection of an error, followed by problem and resolution definition. Once the required resolution has been detected and initiated, the resolution activity is monitored against the planned solution. Where resolution is successful, the issue can be closed.

Where this process breaks down and successful resolution is not achieved, the escalation cycle is invoked. There are three levels of escalation, followed by PAB involvement if resolution and closure of the issue has still not been achieved following intervention at Team Leader, Operations Manager and ELEXON Director level.

Registered office: 4th Floor 350 Euston Road London NW1 3AW   Reg Co No: 3782949 REGISTERED IN ENGLAND AND WALES