The Market-wide Half Hourly Settlement (MHHS) Performance Assurance Framework (PAF) engagement plan supports Elexon’s objectives during the PAF changes due to MHHS. It outlines Elexon’s approach, detailing the audience, purpose, key messages, timing, and engagement methods for key PAF deliverables.
The plan includes key dates for industry stakeholders, related to Settlement Risk resources and changes to Performance Assurance Techniques for the 2025-2026 Performance Assurance Operating Period (PAOP).
MHHS PAT Development for April-25 Implementation
2025/2026 BSC Audit Development
Subject | Method | Date |
PAB BSC Audit workshop | Newscast | Dec 2024 |
UMS BSC Audit Work Paper | Newscast | Sept 2024 |
PAB MHHS BSC Audit Approach Workshop
Elexon will provide a Newscast article to engage Suppliers and Supplier Agents on the key headlines and decisions from the PAB BSC Audit workshop.
The BSC Audit Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered following the workshop due to take place between October and November 2024.
This will highlight any key changes to Parties Audit experience for the BSC Audit beginning in October 2025.
MHHS BSC Audit Work Paper Transformation
All BSC Audit Workpapers are undergoing a MHHS transformation exercise to accommodate new MHHS BSC Procedures and Obligations.
Elexon will provide a Newscast article to engage Suppliers and Unmetered Supplies Operators (UMSO) on the key updates to the UMS BSC Audit Work Paper that was discussed with the P434 Working Group in June 2024.
The UMSO BSC Audit Work Paper will include updates to the Change of Measurement Class processes for P434 Half Hourly Settlement for UMS Metering Systems.
The BSC Audit Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered following the Unmetered Supplies User Group in September 2024.
Code Changes and Guidance Notes
There are no planned BSC PAF related code changes for Section H and the BSC Audit Service Description as part of the MHHS Programme Code Design. PAF will work with the BSC Auditors to implement changes to BSC Audit guidance documents before the start of the 2025/26 BSC Audit beginning in October 2025.
Technical Assurance of Metering (TAM)
Subject | Method | Date |
Technical Assurance of Metering Updates | Newscast | Sept 2024 |
Technical Assurance of Metering Updates | Webinar | Oct 2024 |
Code Changes and Guidance Notes
Elexon will provide a Newscast article to engage Suppliers and Supplier Agents on the updates to the Technical Assurance of Metering (TAM) Guidance Documents, Local Working Instructions, and to BSCP27 – Technical Assurance of Half Hourly Metering Systems for Settlement Purposes.
The update to these documents will accommodate both the changes due to MHHS and the impacts of P432 – Half Hourly Settlement for CT Advanced Metering Systems.
The TAM Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered after M7 (December 2024), prior to the delivery of code changes.
Supplier Charges
Subject | Method | Date |
PAB Supplier Charges workshop | Newscast | Aug 2024 |
Supplier Charges Implementation Date | Newscast | Sept 2024 |
MHHS Supplier Charges PAB Workshop
Elexon will provide a Newscast article to engage Suppliers on the key headlines and decisions that have been taken in the PAB Supplier Charges workshop. The Supplier Charges Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered in August 2024.
MHHS Supplier Charges Implementation Date
Elexon will take a paper to the PAB in August 2024 to determine the implementation date for MHHS Supplier Charges.
The Supplier Charges Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered following a PAB approval of the implementation date paper.
Code Changes and Guidance Notes
A new BSCP710 document is for planned BSC PAF Supplier Charges and there are related code changes for Section S-1 as part of the MHHS Programme Code Design.
The MHHS PAF team will collaborate with the Supplier Charges Code Drafter to implement changes to supplier charges guidance documents before the agreed implementation date.
Performance Assurance Monitoring (PAM)
Subject | Method | Date |
Settlement Performance Reporting | Newscast | Sept 2024 |
Material Error Monitoring Updates | Newscast | Aug 2024 |
Settlement Performance Reporting
Elexon will provide a Newscast to advise Suppliers and Supplier Agents of the updates to Settlement Performance Reporting as a result of MHHS. The Newscast will provide information on the rollout of new MHHS Settlement Performance Reporting.
The EFR lead and MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered following the delivery of the new Performance Standards which will be discussed with the PAB on PAB MHHS Strategy Workshop planned for September 2024.
Material Error Monitoring Updates
Elexon will provide a Newscast to advise Suppliers of the inclusion of Energisation Status Reporting, and Unmetered Supplies Reporting into the Performance Assurance Board Risk Report.
These Changes will remove these reports from the Material Error Monitoring Performance Assurance Technique.
The Risk Report lead and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered in August 2024.
Code Changes and Guidance Notes
The new BSCP711 document planned for BSC PAF to outline PAM is part of the MHHS Programme Code Design incorporates changes to the Peer Comparison technique.
The MHHS PAF team will collaborate with the PAM Code Drafter to implement changes to PAM guidance documents before the start of the 2025/26 PAOP.
Peer Comparison
Subject | Method | Date |
PARMS System Changes | Newscast | Dec 2024 |
PARMS System Changes
Peer Comparison is delivered as part of the legacy PARMS reporting which will be replaced by PAM reporting which will be outlined alongside the MHHS RER which will be taken to PAB in December 2024.
Elexon will provide a Newscast to engage Suppliers and Supplier Agents on the consolidation of publicly available data.
The centralisation of PAB and Public data will reduce the resource required to produce the reporting and prevent duplication of effort. The Peer Comparison Technique Owner and the MHHS PAF Engagement Lead will be responsible for the Newscast which will be delivered by December 2024.
Technical Assurance of Performance Assurance Parties (TAPAP)
Code Changes and Guidance Notes
There are small housekeeping changes planned for BCP535 as part of the MHHS Programme Code Design. There are no expected changes to guidance note documents.
Breach and Default
There are no changes planned for the Breach and Default technique as part of the MHHS Programme Code Design. There are no expected changes to guidance note documents.
Change Mechanism
There are no changes planned for the Change Mechanism technique as part of the MHHS Programme Code Design. There are no expected changes to guidance note documents.