CP0506 – Incorrect estimated settlement data

Formal title: Incorrect estimated settlement data

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

Where an Outage occurs at NGC (either planned or unplanned), the latest received FPNs and BOD received will continue to be used as default by NGC and passed to BMRA, while Bid-Offer Acceptances will be taken by phone and recorded manually for subsequent use. The settlement calculations in BMRA and SAA will not operate correctly without Bid-Offer Acceptance data, resulting in incorrect estimated settlement data being reported by BMRA during NGC outages. Users of the BMRA service will be unaware that the data reported by the BMRA service is incorrect, although a warning message may be issued via BMRA for planned outages.

Progression

This CP was superseded