Summary

For existing CVA Metering Systems where previously approved LLFs have expired and no new ones have been approved, BSCP28 currently states that a value of 1. 00 shall be applied as a default value. The proposed change is that the default values should be the continued use of the current approved LLFs. In addition BSCP28 states that LLFs may have an effective (from) date prior to the date of approval (by the Panel). It is proposed that LLFs cannot have an effective date prior to the date of approval (i. e. no retrospective application).

Progression

This CP was implemented on 13/08/2002