CP0615 – Alignment of the CRA URS with the BSC

Formal title: Alignment of the CRA URS with the BSC

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

Raised from NCR360
BSC Section K 1. 4. 4 makes reference to the capture of information on both Boundary points and System Connection Points. The URS currently makes no reference to the capture of information on System Connection Points. The CRA systems as built and implemented allow capture of all relevant information. Hence this NCR is to align the URS with the Code and with the systems as implemented.

Progression

This CP was implemented in August 2002