CP0662 – Revise timescale associated with SVAA loading the approved LLFs (annual and ad-hoc)

Formal title: Revise timescale associated with SVAA loading the approved LLFs (annual and ad-hoc)

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

Step 3. 2. 9 “Update, Annually or as Required, of SVA LLFs for an Existing LLFC Id” within BSCP528 requires the SVAA to load the LLFs within 5 Working Days of receiving the schedule from the PDSO.
The timescale specified in BSCP528 is too tight for both the annual and the ad-hoc update of LLFs. This activity normally takes around 10 Working Days to complete.

Progression

This CP was implemented