CP0784 – Improvement to process relating to Metering System Proving Tests

Formal title: Improvement to process relating to Metering System Proving Tests

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Rejected

Summary

When a proving test is carried out on a Metering System, the Meter Operator Agent (MOA) informs the Half Hourly Data Collector (HHDC), the Supplier and the Public Distribution System Operator (PDSO) of the outcome (in the case of a failure, only HHDCs are informed). However, there are no procedures in place to cover the case where no notification is received from the MOA on the outcome of the proving test. At present, HHDCs assume that the proving test was successful and use the data in Settlements. This CP has been raised from SIR R1736 ‘Inconsistency in Pool Documentation in respect of Metering System Proving Test’.

Progression

This CP was rejected

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.