CP0816 – Provide half-hourly / non half-hourly SVA data split by BM Unit to National Grid

Formal title: Provide half-hourly / non half-hourly SVA data split by BM Unit to National Grid

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Rejected

Summary

National Grid currently receives the D83 data flow from the SVAA in order to calculate TNUoS charges for Suppliers. The file provides information about the split between half-hourly and non half-hourly energy consumption for each Supplier for each GSP Group. National Grid needs to receive this information split down to the level of individual BM Unit. This level of detail is required for data from 1 April 2002. National Grid will not be reconciling Supplier charges for this year until data is available for the whole financial year (i. e. in May 2003).

Progression

This CP was rejected