Formal title: Revise three of the Serials in PSL110 'SVA Meter Operation'

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Rejected

Summary

Clarify the use of the following three Serials within PSL110: 1. 5. 3. 1, Half Hourly Meter Operator Agent: • Serial 8 “Compare collected data with expected data and send report of unsuccessful test”. • Serial 9 “Compare collected data with expected data and send report of successful test”. 2. 5. 3. 2, Non-Half Hourly Meter Operator Agent:
• Serial 1 “Fault Repairs”.

Progression

This CP was rejected