CP0916 – Timing of the SAAI006 flow from the IA

Formal title: Timing of the SAAI006 flow from the IA

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

There is an inconsistency between the BSC and the requirements in BSCP04. The BSCP requires the Expected Transfer for each Interconnector BM unit to be sent to the SAA ‘By 16. 00 on the WD following the SD’. It is suggested that this text should be changed to read ‘By 24. 00 on the WD following the SD’. A new requirement needs to be incorporated into the table for a IA to contact Elexon if they want to revise BM Unit volumes after the IISR for the relevant Settlement Day.

Progression

This CP was implemented