CP0951
Formal title: Changes and Clarification to HHDA defaulting rules
Current Status
Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented
Summary
Modify a number of Code Subsidiary documents (BSCP503, BSCP508, PSL150 and the SVA Data Catalogue) to: Apply a default consumption value of zero for Half Hourly export meters. Ensure that losses are added to the default. Clarify the derivation of the default value from the EAC of Last Resort
Progression
This CP was implemented