CP0979 – Addition of the Pilot Metercom
Formal title: Addition of the Pilot Metercom
Current Status
Summary
The Pilot Systems Metercom, an independent Data Collection Systems underwent Protocol Approval Testing with the npower Data Collector System on 13 May 2003, in accordance with BSCP601 ‘Metering Protocol Approval and Compliance Testing’. The report of this testing is to be presented to the Supplier Volume Allocation Group (SVG) for approval shortly. BSCP601 states that within 10 Working Days of the approval of the Protocol by SVG, Appendix 3. 3 of BSCP601 ‘Protocol Approval List’ should be updated include the new approved protocol. The progression of this Change Proposal (CP) is subject to the approval of the Pilot Metercom by SVG.
Progression
This CP was implemented