CP1107 – Timescale change to the 100kW notification from NHHDC
Formal title: Timescale change to the 100kW notification from NHHDC
Current Status
Summary
Step 3. 4. 1. 6 of BSCP504 requires the Non-Half Hourly Data Collector, “upon identification”, to notify its Supplier of any occurrence where 100kW has been exceeded (via the P0028 100kw Demand Report). This CP proposes to Simplify and streamline this process by defining a given timescale by when each NHHDC should provide such notification to its Supplier.
Progression
Implemented as part of the November 2005 Release.