CP1153 – Changes to the Meter Advance Reconciliation Processes as detailed in BSCP05

Formal title: Changes to the Meter Advance Reconciliation Processes as detailed in BSCP05

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

CP1153 proposes amendments to BSCP05 regarding the MAR procedures, of Meters both with integral outstations that provide a cumulative reading and Meters with integral outstations that do not provide a cumulative reading of the prime Meter register equivalent to the total consumption or production of that Meter.

Progression

CP1153 was raised on 04 November 2005. CP1153 was issued for Industry Impact Assessment as part of CPC00548. It was approved by Supplier Volume Allocation Group as part of the February 2007 Release.