BSCP504 3. 4. 1. 8 states that each month when 100kW demand is identified by a Non Half Hourly Data Collector (NHHDC) they must produce and send to the Panel and Supplier a report detailing the occurrence. They do this by sending a P0028 ‘100kW Demand Report’ flow. Currently a number of Suppliers assume that if they do not receive a 100kW demand report, the NHHDCs have not identified any items for the Suppliers to follow up. This could potentially lead to the situation where a report has gone missing in transit and the Supplier assumed that no report has been sent. Hence, 100kW demand may not be identified by the Supplier. In response the CP seeks to place a requirement on NHHDCs to send a 100kW Demand Report to Suppliers every month, and where no instances of a 100kW or greater demand occur a ‘nil’ report will be sent. This will prevent the loss of P0028 Demand Reports as the Supplier will expect a report every month, and will be able to contact the NHHDC if a report is not received.

Progression

CP1179 was raised on 15 September 2006. CP1179 was issued for Industry Impact Assessment as part of CPC00590. CP1179 v2. 0 was approved for inclusion in the June 2007 Release by the Supplier Volume Allocation Group on the 05 December 2006.

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.