CP1234 – Movement of the functional requirements within PSL110 to BSCP514 and BSCP550, following the creation of a generic non functional PSL (PSL100) via CP1182.

Formal title: Movement of the functional requirements within PSL110 to BSCP514 and BSCP550, following the creation of a generic non functional PSL (PSL100) via CP1182.

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

The CSD review highlighted a large amount of duplication between the requirements in the PSLs and the corresponding BSCPs. To resolve this issue a single generic PSL has been created under CP1182 ‘Creation of a generic Party Service Line’ which will contain participants’ non-functional requirements. Following on from CP1182, CP1234 was following the implementation of CP1182 and seeks to move the functional requirements of PSL110 ‘SVA Meter Operation’ into BSCP514 ‘SVA Meter Operations for Metering Systems Registered in SMRS’ and BSCP550 ‘Shared SVA Meter Arrangement of Half Hourly Import and Export Active Energy’.

Progression

CP1234 was raised from DCP0026. CP1234 was raised on 29 February 2008. CP1234 was issued for Industry Impact Assessment as part of CPC00629. CP1234 was presented to the ISG on 22 April 2008, the PAB on 23 April 2008 and the SVG on 29 April 2008 for decision on Progression. The ISG, PAB and SVG all approved CP1234 for inclusion in the November 2008 Release.