CP1281 – Revenue Protection: requiring the NHHDC to send EAC/AA data to the Supplier via the DTC

Formal title: Revenue Protection: requiring the NHHDC to send EAC/AA data to the Supplier via the DTC

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

Currently when a Non Half Hourly (NHH) Data Collector (DC) receives advice from the Revenue Protection Business, they are required to record an adjustment to the meter advance based on the unrecorded units estimated by the Revenue Protection Business. The NHHDC then calculates a new Estimated Annual Consumption (EAC) and Annualised Advance (AA) and sends this to the NHH Data Aggregator (DA). CP1281 would require NHHDCs to send all EAC/AAs which have been updated in these circumstances: via a D0019 (BSCP504 does not currently specify this); and to the Supplier as well as the NHHDA.

Progression

CP1281 was raised on 27 February 2009. CP1281 was issued for Industry Impact Assessment as part of CPC00658. CP1281 was presented to the SVG on 05 May 2009 for a decision on progression. The SVG approved CP1281  and it was implemented on 5 November as part of the November 2009 Release

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.