CP1302 – Requirement on Half Hourly Data Collectors to Validate Reactive Power Demand Values
Formal title: Requirement on Half Hourly Data Collectors to Validate Reactive Power Demand Values
Current Status
Summary
The reporting of erroneous Reactive Power data to LDSOs and Suppliers potentially leads to incorrect DUoS charges and other issues. CP1302 recommends extending the scope of existing validation processes to include Reactive Power data. This would reduce errors in those industry processes that use Reactive Power data (e. g. DUoS charging), and reduce the administrative overhead of data errors on Suppliers, LDSOs and customers.
Progression
CP1302 was raised on 03 July 2009. CP1302 was issued for Industry Impact Assessment as part of CPC00666. This CP was approved by the SVG and was implemented as part of the the February 2010 BSC Systems Release.