Summary

On 06/04/09 a new Supply Licence Condition came into effect that required the installation of advanced meters for Profile Class 5-8 sites. On 29/04/10 the MRA Development Board approved an enduring solution in the form of a new data flow.
CP1335 proposes creating the necessary governance over the use of this flow; it needs to be referenced in the relevant BSC Procedures. Furthermore, the data flow includes a new data item, ‘Communications Provider ID’, whose valid set is to be maintained through Market Domain Data.

Progression

CP1335 was raised on 28 May 2010 and was issued for Industry Impact Assessment as part of CPC00681. This CP was approved by the ISG on 27 July and the SVG on 3 August for inclusion in the February 2011 Release.
On 17 January, the SVG and ISG agreed (by correspondence) that CP1335 should instead be implemented on 3 November 2011, as part of the November 2011 Release. This aligns the implementation of CP1335 with a related DTC CP which was deferred by the MRASCo Development Board on 5 January.