CP1423 – Amendments to BSCP68 following a review

Formal title: Amendments to BSCP68 following a review

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Rejected

Summary

CP1423 proposed changes to BSCP68 to clarify procedures and amend steps so that they are consistent with other BSCPs.

Progression

CP1423 was raised on 14 November 2014. CP1423 was presented to the ISG and SVG as part of the New CP Assessment paper on 25 November 2014 and 2 December 2014 respectively. CP1423 was issued for CP Consultation on 8 December 2014, with responses due back by 9 January 2015. CP1423 was rejected the ISG and SVG  at their meetings on 27 January 2015 and 3 February 2015 respectively.