CP1430 – Clarification to the ECVN/MVRN processes

Formal title: Clarification to the ECVN/MVRN processes

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

CP1430 proposes to clarify instances of ambiguous or unclear advice regarding the Energy Contract Volume Notification (ECVN) and Metered Volume Reallocation Notification (MVRN) processes. In particular CP1430 will better enhance the clarity of the methods for terminating these notifications.

Progression

CP1430 was raised by Elexon on 9 February 2015 and has been issued for CP Consultation. The ISG approved CP1430 on 21 April 2015 for implementation on 5 November 2015 as part of the November 2015 BSC Systems Release.