CP1445
Formal title: BSCP516 alignment with revised P272 Implementation Date
Current Status
Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented
Summary
CP1445 proposes to amend references to the P272 Implementation Date within BSCP516 from ‘1 April 2016’ to ‘1 April 2017’ to reflect the extension granted to this date.
Progression
CP1445 was raised by Elexon on 24 July 2015. The SVG approved CP1445 as a Housekeeping CP on 4 August 2015 for implementation on 11 August 2015.