CP1458 – Introduction of timescales for the P283 Commissioning process for SVA CT operated Metering Systems

Formal title: Introduction of timescales for the P283 Commissioning process for SVA CT operated Metering Systems

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

CP1458 seeks to introduce timescales in relation to activities performed during the Commissioning process and with the communications obligations introduced under Modification P283. The proposed timescales relate to the LDSO, MOA and Supplier activities and only apply to the SVA market and CT operated Metering Systems.

Progression

CP1458 was raised by Elexon on 16 February 2016. The new CP Progression Paper was presented to the SVG for information on 1 March 2016 and issued for CP Consultation on 7 March 2016, with responses due by 1 April 2016. CP1458 v2.0 is currently out for Industry Consultation in the July CPC batch with responses due back on Friday 5 August 2016. CP1458 will be presented to the SVG for decision on 6 September 2016. The SVG approved CP1458 with version 2.0 redlining at its meeting on 6 September 2016 for implementation on 3 November 2016 as part of the November 2016 BSC Release.

Next Events

CP1458 with version 2.0 redlining was implemented on 3 November 2016 as part of the November 2016 BSC Release.