Change Proposal: CP1494

Introduction of an objection window for Housekeeping Change Proposals

Proposer: ELEXON

Current Phase: Implemented

Category: Not Applicable

Responsible Panel Committees: Imbalance Settlement Group (ISG), Supplier Volume Allocation Group (SVG)

Implementation Date: 22 February 2018 (February 2018 Release)

Summary

Currently, Parties have the ability to object to Modification ‘housekeeping’ changes only and not Housekeeping Change Proposals (CP). This creates inconsistent governance principles between the Modification and CP processes. ELEXON is seeking to introduce an equivalent 15 Working Day (WD) objection window into the Housekeeping CP process in BSCP40.

ELEXON still believes that an industry consultation is not needed for Housekeeping CPs. However, we are seeking to introduce an objection window into the process.

This CP will amend BSCP40 (sections 3.4 and 3.5) to introduce a 15 WD objection window for Housekeeping CPs. Our objection process is broadly in line with the Fast Track Self-Governance Modification Proposals process.

 

Progression

CP1494 was raised by ELEXON on 13 September 2017. The CP Progression paper was presented to the ISG and SVG for information at its meetings on 26 September 2017 and 3 October 2017 respectively. The CP was issued for CP Consultation on 9 October 2017. This CP was presented to and approved by  the SVG on 5 December and ISG on 11 December and implemented on 22 February 2018.

Documents

CP1494 - Final Report  [507.4 Kb]
Document Date: 15 December 2017

CP1494 CP Consultation Responses  [176.5 Kb]
Document Date: 10 November 2017

CP1494 - CP Consultation  [629.1 Kb]
Document Date: 9 October 2017

CP1494 - Progression Paper (ISG198/09)  [772.5 Kb]
Document Date: 26 September 2017

CP1494 - Proposal Form  [482.4 Kb]
Document Date: 13 September 2017