Where Metering Equipment has been installed by a non-BSC Party, the BSC places obligations on the  Registrant to ensure that its MOA performs the required Commissioning of all Metering Equipment in  accordance with CoP4, which includes Commissioning and testing of measurement transformers (current transformers (CTs) and voltage transformers (VTs)).

However, there is no guidance regarding situations where measurement transformers installed by a non-BSC Party are later adopted by a BSC Party. 

CP1528 seeks to amend CoP4 to clarify that a BSC Party will be responsible for the Commissioning of any measurement transformers that the BSC Party has agreed to adopt.

Podcast

Listen to the complete BSC Party responsibility for Commissioning of measurement transformers podcast:

If you would like a transcript for the CP1528 podcast then please email bsc.change@elexon.co.uk.

Progression

CP1528 was raised on 28 January 2020. It was presented to the ISG and SVG on 4 February 2020 and issued for consultation as part of the Feburary 2020 CPC batch. The CP1528 Assessment Report was presented to the April 9 ISG and SVG for decision and CP1528 was unanimously approved for implementation on 5 November 2020 as part of the November 2020 BSC Release.

Next Events

CP1528 will be implemented on 5 November 2020 as part of the November 2020 BSC Release.

My ELEXON

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of ELEXON insights

ELEXON Circulars

Training services delivered by ELEXON

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or