CP1531 ‘Additionally provide the TUoS Report to National Grid ESO at the II Settlement Run’
Formal title: Additionally provide the TUoS Report to National Grid ESO at the II Settlement Run
Additionally provide the TUoS Report to National Grid ESO at the II Settlement Run
National Grid ESO requires the Balancing and Settlement Code Company (BSCCo) to provide the Transmission Use of System (TUoS) Report at the II (Interim Information) Settlement Run to ensure they can continue to provide an indicative view of Balancing Services Use of System (BSUoS) charges to liable parties after the introduction of a proposed change to the charging methodology.
The BSCCo shall generate and publish the P0210 TUoS Report (HH/NHH Split) at the II Settlement Run, make it available on the Elexon Portal, and deliver to National Grid ESO via file transfer. The TUoS Report is already generated and published for subsequent Settlement Runs as it is needed for the calculation of Transmission Network Use of System (TNUoS) charges.