CP1567 ‘New BSC Procedure (BSCP) for Assurance Information Requests (AIRs)’

The AIR is a Performance Assurance Technique (PAT) which was introduced in May 2022. Currently there is no related BSCP for an AIR, therefore when issuing an AIR, there is no written obligation on Parties to adhere to the request.

Read More

CP1559 ‘Complex Sites Process Improvements’

This Change Proposal will deliver improvements to the Complex Sites process.

Read More

P441 ‘Creation of Complex Site Classes’

This Modification looks to progress a recommendation of the Issue 88 Workgroup to introduce Complex Site classes. These classes would categorise the types of Complex Site, each having clearly defined criteria within the BSC. A new “type” of Complex Site (referred to as a Class 6 Complex Site) to allow approval of ”non-standard” complex sites would also be introduced.
P441 would also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted.

This change would facilitate consistency across the market and as so called “Local Energy Schemes” become more popular, rules for when netting are permitted would be clearly defined going forward.

Read More

P427: Publication of Performance Assurance Parties’ impact on Settlement Risk

This Modification seeks to amend BSC Section Z to allow the Performance Assurance Board (PAB) to recommend that the Panel publish notices to industry in respect of Performance Assurance Parties’ (PAPs’) contribution to Settlement Risk along with relevant risk data.

Read More

CP1563 ‘Altering the Trigger Point and subsequent Timescales for Commissioning SVA CT Operated Metering Systems and issue of Data Flow’

CP1563 seeks to update some of the trigger points for Current Transformer (CT) Commissioning and subsequent sending of data flows as the Proposer considers that they are not appropriate for CT operated metering systems of all types.

Read More

P438 ‘Amending the BSC to address sanction orders’

This Modification would allow Elexon to seamlessly give effect to sanctions orders.

Read More

P436 ‘Consequential BSC changes for Switching SCR (REC 3.0)’

Ofgem’s Switching Significant Code Review (SCR) will introduce the new Central Switching Service (CSS) and version 3.0 of the Retail Energy Code (REC 3.0). P436 progresses the consequential BSC changes needed to align with REC 3.0. 

Read More

P437 ‘Allowing non-BSC Parties to request Metering Dispensations’

This Modification proposes to introduce a provision in Section L ‘Metering’ to allow the relevant Meter Operator Agent to apply for Metering Dispensations on behalf of a non-BSC Party.

Read More

CP1558 ‘New Registration data items to facilitate MHHS’

This Change Proposal will introduce new Registration Service data items and supporting BSC processes into existing Supplier Meter Registration Service (SMRS) systems. 

Read More

CP1554 ‘Future proofing the measurement transformer standards’

CP1554 looks to future proof the  measurement transformer standards in Code of Practices 1, 2, 3, 4, 5 and 10

Read More

CP1553: Meters and Current Transformers minimum accuracy classes

This Change proposal looks to tighten the requirements for Meters and Current Transformers in the Code of Practice.

Read More

CP1550: Updates to monitoring of voltage failure alarms requirements

This Change Proposal looks to simplify the management of phase failures and update the requirements of voltage failure alarms.

Read More

P432 ‘Half Hourly Settlement for CT Advanced Metering Systems’

This Modification proposes to align the BSC definition of an Advanced Meter with that in the Standard License Conditions (SLC) and to set explicit Half Hourly (HH) Settlement obligations for Current Transformer (CT) Advanced Meters ahead of the migration to Market-wide Half-Hourly Settlement (MHHS). 

Read More

P434 ‘Half Hourly Settlement for UMS Metering Systems’

This Modification will require a period of mandatory Change of Measurement Class (CoMC) activity for all Non-Half Hourly (NHH) Unmetered Supplies (UMS) Metering Systems running from October 2023 to October 2024. It will also require all new UMS connections to be settled Half Hourly (HH) from October 2023. 

Read More

CP1560 ‘Demand Control Event Process Clarifications’

This CP seeks to clarify the processes that take place after a Demand Control Event by amending the relevant Code Subsidiary Documents to ensure clarity and consistency. 

Read More

CP1555 ‘Consumption data for Measurement Classes G and F’

This CP proposes to update the requirements in BSCP502 to require HHDCs to send D0036 or D0275 for non-Data Communications Company (DCC) enrolled Metering Systems and/or D0380 for DCC enrolled Metering Systems to Licenced Distribution System Operators (LDSOs).

Read More

P416 Introducing a route of appeal for the Annual Budget in line with the proposals for the Retail Energy Code

P416 seeks to amend the BSC to include an appeals mechanism that BSC Parties could use to challenge items in the Annual Budget.

Read More

CP1547 ‘Clarification on Site Specific LLF Calculation Process for Embedded LDSOs’

CP1547 seeks to provide clarity for Embedded LDSOs that choose to calculate Site Specific Line Loss Factors rather than Mirroring, through updates to BSCP128. 

Read More

P424 ‘Re-insert correct definition of Settlement Error’

Read More

P423 ‘Market-wide Half Hourly Settlement (MHHS) Implementation and Governance Arrangements’

Read More

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of BSC Insights

Previous Circulars

Training videos and services

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or