BSC Changes impacting Meter Administrators
This page shows which Modifications and Change Proposals have been identified as impacting Meter Administrators. Please note that the assessment of where impacts may affect certain roles within the electricity market may be amended during the course of the Change process.
P463 ‘Introduce a Standard Change Process’
To introduce a new change process – a ‘Standard Change’ process – into the BSC arrangements that would allow for certain, low risk, predictable and repeatable pre-authorised changes to be implemented without following the existing Change Proposal or Modification procedures.
If you are interested in joining the P463 Workgroup, please sign up via the Modification and Issue Workgroup sign-up webpage.
P456 ‘Enable Elexon to procure ancillary Technology Services for use by BSC Agents’
Removing barriers in BSC Section E that would prevent Elexon updating BSC Agent contracts, therefore enabling BSC Agents to use Technology Services procured by Elexon. This should reduce costs for BSC Parties.
P427: Publication of Performance Assurance Parties’ impact on Settlement Risk
This Modification seeks to amend BSC Section Z to allow the Performance Assurance Board (PAB) to recommend that the Panel publish notices to industry in respect of Performance Assurance Parties’ (PAPs’) contribution to Settlement Risk along with relevant risk data.
CP1567 ‘New BSC Procedure (BSCP) for Assurance Information Requests (AIRs)’
The AIR is a Performance Assurance Technique (PAT) which was introduced in May 2022. Currently there is no related BSCP for an AIR, therefore when issuing an AIR, there is no written obligation on Parties to adhere to the request.
P434 ‘Half Hourly Settlement for UMS Metering Systems’
This Modification will require a period of mandatory Change of Measurement Class (CoMC) activity for all Non-Half Hourly (NHH) Unmetered Supplies (UMS) Metering Systems to complete before the Market Wide Half Hourly Settlement (MHHS) migration to the Target Operating Model (Milestone 11 (M11) in the MHHS Timetable). At the time of writing, this would need to complete by October 2024. It will also require all new UMS connections to be settled Half Hourly (HH) from 12 months prior to M11, currently October 2023.
CP1565 ‘Updates to address Central Management System issues’
This CP seeks to update BSCP520 to contain clearly outlined processes for approval and fault reporting of Central Management Systems.
CP1559 ‘Complex Sites Process Improvements’
This Change Proposal will deliver improvements to the Complex Sites process.
CP1546 ‘Introducing DTC flows to transfer UMS Summary Inventories and Control files’
CP1561 ‘Updating SVA DC Volume 1 and 2 for CP1546’
CP1561 looks to update the Supplier Volume Allocation (SVA) Catalogue Volume 1 and 2 to include the approved data flows and data items from CP1546.