P356 Report Phase Consultation

Status

Who will this impact?

P356 will align the BSC with Grid Code Modification GC0099, which seeks to introduce the Interconnector Scheduled Transfer process to the Grid Code. This is in order to establish common, cross-code provisions which are compatible with both the EU single intraday market coupling processes, and GB and EU balancing processes. The P356 Assessment Report was presented to the Panel on 8 February 2018 and the Panel is now consulting on their views ahead of the Draft Modification Report being presented to the Panel on 8 March 2018.