P089 – Clarification Of The Timescales For Submitting MEL/MIL Data To The BMRA

Formal title: Clarification Of The Timescales For Submitting MEL/MIL Data To The BMRA

Current Status

Submission
Initial Written Assessment
Assessment Procedure
Report Phase
With Authority
Awaiting Implementation
Implemented

Summary

This proposal seeks to align the BSC with existing practices and systems with regard to the Maximum Export Limit/Maximum Import Limit (MEL/MIL) received by the National Grid Company.

Progression

The Authority approved the Proposed Modification on 1 May 2003. P89 was implemented on 23 May 2003.