P174, when implemented in November this year, will allow BM Units associated with Interconnector that has a single Boundary Point to form Trading units and it had been fully assumed and expected by all concerned that the Anglo-French Interconnector would qualify (i.e. that the Anglo-French Interconnector has a single Boundary Point and would be captured by P174). However, it has become apparent in preparing for the implementation that the Anglo-French Interconnector has been registered with two Boundary Points, albeit at the same site, thus precluding BM Units associated with this Interconnector from forming Trading Units as envisaged under P174.
Progression
The Authority approved the Proposed Modification on 9 September 2005.