EL02397: Resolutions from BSC Panel Meeting regarding Defaulting Party Emexconsult Ltd [122.0 Kb] Issue Date: 10 March 2016

At its meeting on 10 March 2016 the BSC Panel noted that Emexconsult Ltd (registered number NI614354) is in default of BSC Section H3.1.1(b) and passed resolutions set out in this Circular.

EL02396: Correction: Decrease in the Credit Assessment Price (CAP) to £33/MWh from Tuesday 5 April 2016 [112.0 Kb] Issue Date: 9 March 2016

This Circular is published as a correction to ELEXON Circular EL02394 stating that the new Credit Assessment Price (CAP) value would be implemented on Monday 4 April. A system restriction prevents implementing a new CAP value on a Monday. The revised effective date will be Tuesday 5 April 2016.

EL02395: Planned National Grid BM Outage delayed until Thursday 17 March 2016 [114.4 Kb] Issue Date: 8 March 2016

Further to ELEXON Circular EL02391 we have been notified by National Grid that the Balancing Mechanism (BM) planned outage will now take place between 10:10 (GMT) and 13:10 (GMT) on Thursday 17 March 2016. The original date for this planned outage was Thursday 10 March 2016.

EL02394: Decrease in the Credit Assessment Price (CAP) to £33/MWh from Monday 4 April 2016 [110.5 Kb] Issue Date: 8 March 2016

Following consultation with Trading Parties, the Credit Committee agreed to decrease the Credit Assessment Price (CAP) value to £33/MWh from Monday 4 April 2016.

EL02393: Planned BSC Agent downtime impacting REMIT and Transparency pages on BMRS on 9-10 March 2016 [111.8 Kb] Issue Date: 8 March 2016

There will be planned downtime on the REMIT and Transparency pages on the Balancing Mechanism Reporting Service (BMRS) taking place between 23:00 (GMT) on Wednesday 9 March and 07:00 (GMT) on Thursday 10 March 2016.

EL02392: Restart of pricing data post November 2015 release issues [124.1 Kb] Issue Date: 4 March 2016

This Circular provides information on National Grid’s next steps to re-establish the reporting of price data to the market. De–rated Margin (DRM) data feeds and Balancing Mechanism (BM) Short Term Operation Reserve (STOR) flagging solutions will resume at 12:00 on Monday 7 March 2016.

EL02391: Planned National Grid BM outage – Thursday 10 March 2016 [112.0 Kb] Issue Date: 3 March 2016

National Grid has notified us that there will be a Balancing Mechanism (BM) planned outage between 10:10 (GMT) and 13:10 (GMT) Thursday 10 March 2016.

EL02390: Planned BSC Agent downtime on BMRS: 2–3 March 2016 [111.0 Kb] Issue Date: 29 February 2016

There will be planned downtime on the REMIT and Transparency pages of the Balancing Mechanism Reporting Service (BMRS) between 23:00 (GMT) Wednesday 2 March and 07:00 (GMT) Thursday 3 March 2016.

EL02389: Risk Evaluation Methodology 2017/18 consultation published [109.8 Kb] Issue Date: 29 February 2016

This consultation asks respondents to review the Risk Evaluation Methodology 2017/18 and submit any comments to Melinda Anderson by Friday 18 March 2016.

EL02388: Update on post November 2015 release pricing issues [138.0 Kb] Issue Date: 26 February 2016

Further to ELEXON Circular EL02386 National Grid has confirmed that system testing for the planned solution to post November 2015 release pricing issues remains on track and they are currently completing the final tests.