November 2020 BSC Release

Scope of the Release

The approved implementation date for this release is 5 November  2020.

The scope of this release is three approved Modifications and two approved  Change Proposals. 

Approved

P396: Revised treatment of BSC Charges for Lead Parties of Interconnector BM Units

P409: Aligning BMRS Reporting Requirements with the Clean Energy Package

P411: Including new LDSOs in Qualification to mitigate potential risks to Settlement

CP1528: CoP4 clarification of BSC Party responsibility for Commissioning of measurement transformers that the BSC Party adopts

CP1529: Earlier initiation of Supplier Agreed Meter Readings process 

 

November 2020 Release - Document Impact Matrix