The Change Proposal Consultation Impact Assessment Timetable provides the dates that the monthly Change Proposal Consultations will be issued. 

We publish consultations for Change Proposals (amendments to BSC subsidiary documents), and in particular when requesting Impact Assessment responses from Industry Participants. These are grouped together monthly and published on the List of Change Proposal Consultations webpage.

Unlike Modifications, consultations on Change Proposals (CPs) have to be issued in accordance with a fixed timetable. BSCP40 ‘Change Management’ requires CPs be issued for industry consultation as part an agreed timetabled Change Proposal Consultations ‘batch’.

The following timetable denotes timetable for these consultations and is known as the Change Proposal Impact Assessment Timetable.

 Change Proposal Consultation

Committee Decision

Month
Issued
Responses Due
Responses Published by Date
Meeting Date ISG/SVG
Meeting Date PAB
November 13 Nov 23 8 Dec 23 15 Dec 23 9 Jan 24 14 Dec 23
December 11 Dec 23 10 Jan 24 17 Jan 24 6 Feb 24 25 Jan 24
January 15 Jan 24 9 Feb 24 16 Feb 24 5 Mar 24 29 Feb 24
February 12 Feb 24 8 Mar 24 15 Mar 24 2 Apr 24 28 Mar 24
March 11 Mar 24 9 Apr 24 16 Apr 24 7 May 24 25 Apr 24
April 8 April 24 3 May 24 13 May 24 4 Jun 24 30 May 24
May 13 May 24 10 Jun 24 17 June 24 2 Jul 24 27 Jun 24
June 10 Jun 24 5 Jul 24 12 Jul 24 6 Aug 24 25 Jul 24
July 8 Jul 24 2 Aug 24 9 Aug 24 3 Sep 24 29 Aug 24
August 12 Aug 24 9 Sep 24 16 Sep 24 1 Oct 24 26 Sep  24
September 9 Sept 24 4 Oct 24 11 Oct 24 5 Nov 24 31 Oct 24
October 7 Oct 24 1 Nov 24 8 Nov 24 3 Dec 24 28 Nov 24
November 11 Nov 24 6 Dec 24 13 Dec 24 14 Jan 25 (TBC) 19 Dec 24 (TBC)

 