Smart Meter Technical Detail Report

Glossary

The Smart MTD report is used to monitor compliance with BSC obligations over the foundation and mass roll-out phases of the smart Meter roll-out. 

It provides: market level performance at sending late and corrected MTDs for both Smart Metering Equipment Technical Specification (SMETS) v1.0 and v2.0 Meters;  volumes of meter installations completed by meter type; and performance at first reconciliation run for all meter types.

Please note: This report is based on Meter Technical Details sent over the Data Transfer Network. It provides an insight into market performance, but not a complete view.

Summary of the data

During December 2020 SMETS v2.0 installs constitute the majority of exchanges (87.27% of total Meter installs over the month). 

The number of SMETS v2.0 installs in December 2020 decreased from 188k to 144k. The proportion of late MTDs for SMETS v2.0 exchanges has decreased (3.41% in November 2020 to 3.40% in December 2020).

The proportion of corrected MTDs for SMETS v2.0 exchanges has decreased (1.08% in November 2020 to 1.07% in December 2020). The total number of SMETS v2.0 exchanges is still too low to raise concerns.

We note that in the December 2020 reporting period, the number of SMETS v1.0 Meters installed decreased from 8k in November 2020 to 6k in December 2020. 

Data for December 2020 reporting period

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of BSC Insights

Circulars

BSC training services

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or