Glossary

Treatment of Volume Notification on clock change day: 28 October 2018

UK time changes on Sunday 28 October 2018 from British Summer Time to Greenwich Mean Time. This will result in a ‘long’ day where there are 50 Settlement Periods instead of the standard 48.

What is happening?

As the clocks go back an hour on a ‘long’ clock change day, there are 50 Settlement Periods instead of the standard 48.

Settlement Periods one to four inclusive on 28 October 2018 will begin as normal at 00:00 (BST), 00:30 (BST), 01:00 (BST) and 01:30 (BST) respectively.

At 02:00 (BST), the clocks will change to GMT so instead of Settlement Period five beginning at 02:00 (BST), Settlement Period five will begin at 01:00 (GMT).

Settlement Period six will begin at 01:30 (GMT) and so on until Settlement Period 50 begins at 23:30 (GMT).

How will I be affected?

The ECVAA Notification Report (ECVAA-I014) report for 28 October 2018 will contain 50 Settlement Periods and will include the effect of any defaulting rules applied to multi-day notifications.

The ECVAA Forward Contract Report (ECVAA-I022) for 28 October 2018 will show a representation of the original notifications submitted.

What do I need to do?

Submitting a contract notification which includes both the clock change day and normal days

If you submit a contract notification which includes the clock change day and normal, non-clock change days, Energy Contract Volume Aggregation Agent (ECVAA) default rules apply.

The notified volumes corresponding to Settlement Periods three and four will also be applied to Settlement Periods five and six on the clock change day.

Notified volumes for the remaining Settlement Periods on the clock change day will all be used for the Settlement Period, two Settlement Periods later than the one they were originally notified for.

Submitting a contract notification for the clock change day alone

If you submit a contract notification for the clock change day alone, the Settlement Periods in the contract notification should be numbered from 1 to 50.

Please note that contract notifications for the clock change day alone must contain the correct number of Settlement Periods as no defaulting rules will be applied to these notifications.

Is there anything else I need to know?

No.