CP1242 – Movement of the functional requirements within PSL180 CVA Meter Operation into BSCP06
Formal title: Movement of the functional requirements within PSL180 CVA Meter Operation into BSCP06
Current Status
Summary
The CSD review highlighted a large amount of duplication between the requirements in the PSLs and the corresponding BSCPs. To resolve this issue a single generic PSL has been created under CP1182 ‘Creation of a generic Party Service Line’ which will contain participants’ non-functional requirements. Following on from CP1182, CP1242 seeks to move the functional requirements of PSL180 ‘CVA Meter Operation’ into BSCP06.
Progression
CP1242 was raised on 29 February 2008. CP1242 was issued for participant Impact Assessment on 11 April 2008. CP1242 was presented to the PAB on 21 May 2008 for decision on progression. The PAB approved CP1242 for inclusion in the November 2008 Release. CP1242 was presented to the ISG on 27 May 2008 for decision on progression. The ISG approved CP1242 for inclusion in the November 2008 Release. CP1242 was presented to the SVG on 03 June 2008 for decision on progression. The ISG approved CP1242 for inclusion in the November 2008 Release.