CP1443 – Standard Settlement Configurations for smart and advanced Meters
Formal title: Standard Settlement Configurations for smart and advanced Meters
Current Status
Summary
CP1443 proposes to add a new requirement to BSCP516 section 4.2 to help Suppliers avoid mixing Radio Teleswitch Service (RTS) and smart Metering Systems on the same Standard Settlement Configuration (SSC). This will facilitate Supplier reporting of RTS migration.
Progression
CP1443 was raised by Elexon on 12 May 2015. CP1443 was presented to the SVG as part of the New CP Assessment paper at its meeting on 2 June 2015. It was issued for CP Consultation on 8 June 2015, with responses due by 3 July 2015. CP1443 was approved by the SVG at its meeting on 4 August 2015 and implemented on 25 February 2016 as part of the the February 2016 Release.