CP1456 – Clarification to BSCP514 regarding the sending of Meter Technical Details on receipt of a D0170 data flow
Formal title: Clarification to BSCP514 regarding the sending of Meter Technical Details on receipt of a D0170 data flow
Current Status
Summary
CP1456 proposes to amend BSCP514 to align the MOA obligations with those for NHHDCs (as detailed in BSCP504) that Meter Technical Details should be sent on receipt of a D0170 ‘Request for Metering System Related Details’ data flow, irrespective of whether a D0151 ‘Termination of Appointment or Contract by Supplier data flow has been received from the Supplier.
Progression
CP1456 was raised by Elexon on 15 January 2016. The new CP Progression Paper was presented to the SVG for information on 2 February 2016 and issued for CP Consultation on 8 February 2016, with responses due by 4 March 2016. The SVG approved CP1456 at its meeting on 5 April 2016 for implementation on 30 June 2016 as part of the June 2016 Release.