CP1526 ‘Introduction of Service Level Agreements for rectifying Meter faults’
CP1526 seeks to introduce formal Service Level Agreements that should be adhered to by Meter Operator Agents (MOAs) and Licensed Distribution System Operators (LDSOs) when rectifying Half Hourly Meter faults to ensure continued overall accountability of rectifying faults on Metering Equipment.
Formal title: Introduction of Service Level Agreements for rectifying Meter faults
Current Status
Progression
CP1526 was presented to the SVG for decision on 3 March 2020 and the PAB on 26 March 2020 where it was rejected.
CP1526 was issued for CP Consultation on 13 January 2020, with responses invited by 7 February 2020.
The Progression paper for CP1526 was presented to the SVG at its meeting on 7 January 2020.
CP1526 was raised by Elexon on 13 December 2019.
Next Events
CP1526 was rejected by the SVG on 3 March 2020 and the PAB on 26 March 2020.