P205 – Increase in PAR level from 100MWh to 500MWh

Formal title: Increase in PAR level from 100MWh to 500MWh

Current Status

Submission
Initial Written Assessment
Assessment Procedure
Report Phase
With Authority
Awaiting Implementation
Implemented

Summary

The purpose of this Modification is to amend the PAR level introduced with the introduction of P194 of 100MWh to 500MWh, which will lessen the impact of P194 on smaller parties, in particular variable renewable generators, within the market.

Progression

Authority approved the Proposed Modification on 20 October 2006. P205 was implemented on 2 November 2006 as part of the November 2006 BSC Systems Release.