CP1485
Formal title: Validation of power transformer and cable/line loss adjustments
Current Status
Summary
This CP proposes changes to the BSCP32, Code of Practices (CoPs) 1, 2, 3, and 5 to address the validation of power transformer and cable or line electrical loss adjustments as part of the Metering Dispensation application process.
Progression
CP1485 was presented for information to the ISG on 28 March 2017 and to the SVG on 4 April 2017. This CP Consultation closed on 5 May 2017. The CP was presented for decision at the ISG meeting on 23 May 2017. CP1485 was approved at the ISG meeting on 23 May 2017 and the SVG meeting on 30 May 2017. CP1485 was implemented on 2 November 2017 as part of the November 2017 Release.