Change consultations

This page lists all Change Consultations which are opened when we need to obtain feedback from the industry on potential Modifications, Change Proposals and Issues. The page also includes Change consultations which have ceased to be active as they have reached their closed date.

(Showing items 6-10 of 193)

Show 5 | 10 | 20 | All

P380 Report Phase Consultation

Summary

Recent changes to the Replacement Reserve Implementation Framework (RRIF), specifically the Transmission System Operator (TSO) energy bid submission gate closure time for Replacement Reserves (RR), mean that National Grid as the GB Electricity System Operator (ESO) will not be able to be compliant with the Balancing and Settlement Code (BSC) obligations introduced under Modification P344 ‘Project TERRE implementation into GB market arrangements’.

This Modification proposes to modify the  BSC Section Q ‘Balancing Mechanism Activities’ wording introduced by P344 to ensure National Grid ESO’s continued compliance with the BSC and the RRIF.

P363 and P364 Assessment Consultation

Summary

Following ELEXON’s review of Metering Dispensation the decision was made to raise two separate Modifications, P363 ‘Simplifying the registration of new configurations of BM Units’ and P364 ‘Clarifying requirements for registering and maintaining BM Units’, to address the issues that were found. Separate Modifications were proposed to address the two different defects at hand. It was thought that by keeping the Modifications separate we avoid the possibility of them being dependent on each other when it comes to approval and/or rejection. 

The combined P363/4 Workgroup identified a single solution that will remedy both the P363 and P364 defects. The proposed solution for P363/4 has four elements:

  • Expand BSC Section K ‘Classification and registration of Metering Systems and BM units’ Section 3 criteria for those BM Unit configurations that are deemed to meet the conditions to be registered as a Standard BM Unit;
  • Lay down new criteria for what is considered to be a Standard BM Unit;
  • Change the BSC so that an application to register BM Units must either meet the configuration criteria (bullet one above) or align with the new list of registration criteria (bullet two above) to be considered as a Standard BM Unit; and
  • Removing the need to apply for a Non-Standard BM Unit where the configuration is Standard but there is more than one Party involved.

P378 Modification Consultation

Summary

We have issued Urgent Modification Proposal P378 ‘ Introduction of a CM Supplier Interim Charge’ for industry consultation, with responses invited by 5pm on Tuersday 29 January 2019.

P378 seeks to use the BSC to introduce a CM Supplier Interim Charge for Suppliers. This will act as a contingency fund to protect the industry, and customers, from a price shock in the event that the CM standstill is lifted and back payments are required to be made. The Modification solution is based on the recommendations of Issue 76.

P370 Report Phase Consultation

Summary

We have issued P370 ‘Allow the Panel to designate non-BSC Parties to raise Modifications’ for Report Phase Consultation,  interested parties were invited to respond by Friday 25 January 2019. P370 seeks to allow the BSC Panel, instead of Ofgem, to designate interested third parties to raise Modification Proposals and for Ofgem to become the appeals body. P370 also opens up the Issues process to non-BSC Parties. 

P377 Amending Gate Closure references in Market Index Data

Summary

BSC Section T 1.5.3(b)(iii) defines ‘short term’ in relation to Market Index Data as a time period in reference to Gate Closure. Following BSC Modification P342 implemented in November 2017, the deadline for contracts for delivery in a Settlement Period has moved from Gate Closure to the Submission Deadline. P342 did not change the Market Index Definition Statement (MIDS) to reflect this. The 2018 MIDS Review is proposing to amend references of Gate Closure to the Submission Deadline to include trades taken in the hour prior to a Settlement Period in Market Index Data which will impact Market Index Data Providers. This change to the MIDS will need BSC Panel approval in November and approval from the Authority.

P370 Assessment Procedure Consultation

Summary

We have issued P370 ‘Allow the Panel to designate non-BSC Parties to raise Modifications’ for Assessment Procedure Consultation, which you are invited to respond to by Monday, 12 November 2018. P370 seeks to allow the BSC Panel, instead of Ofgem, to designate interested third parties to raise Modification Proposals and for Ofgem to become the appeals body. P370 also opens up the Issues process to non-BSC Parties.

P369 Report Phase Consultation

Summary

P369 proposes to modify the Balancing Settlement Code (BSC) to reflect the creation of a new National Grid Electricity System Operator (NGESO) that is legally separate from National Grid Electricity Transmission Limited (NGET). Further information can be found on the P369 webpage.

This is the P369 Report Phase Consultation, whereby industry views are requested in respect of the BSC Panel’s initial recommendations on the Modification.

P361 Report Phase Consultation

Summary

P361 seeks to exclude Interconnector Balancing Mechanism (BM) Units from the Main Funding Share and SVA (Production) Funding Share BSC Charges, in order to better facilitate the EU Third Package.

P362 Report Phase Consultation

Summary

P362 seeks to enable BSC Parties to be derogated against specific BSC obligations in order to trial pre-competitive and innovative products and services.

P368 Report Phase Consultation

Summary

P368 shall amend provisions in the timing and revision of the Performance Assurance Framework  (PAF) Procedure documents in order to support the objectives of the PAF Review in delivering a more efficient and effective PAF.  Further information can be found on the P368 webpage.

This is the P368 Report Phase Consultation, whereby industry views are requested in respect of the BSC Panel’s initial recommendations on the Modification.

My ELEXON

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of ELEXON insights

ELEXON Circulars

Training services delivered by ELEXON

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or